18-30 Erskine Avenue Construction

Update: November 22, 2017

Shoring lagging work and excavation continue to progress.  In the excavated area, we are installing tiebacks and forming our internal staging area. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

To facilitate shoring and tiebacks along Erskine Avenue, KG has obtained a temporary street occupation permit to close the sidewalk and curb lane at our site from Monday November 6 to the end of December.

During the closure, two-way traffic is to be maintained at all times in the eastbound lane on Erskine Avenue. There are two full-time certified traffic controllers to control traffic for our site; they will stop vehicular traffic to allow pedestrians to walk through the closure.

Once again, we would like to remind the John Fisher Junior Public School Community that the designated vehicular drop-off area by JFJPS is the Kiss and Ride area on Keewatin Avenue. In addition, alternative walking routes include using Keewatin Avenue or walking along the south side of Erskine Avenue and crossing at Redpath Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. We continue to observe trucks for other projects parking and idling on Erskine Avenue. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

 

Update: November 8, 2017

Safety always has been and continues to be our number one priority. We want to take this opportunity to reiterate how critically important the safety of students and parents is to us. So much so in fact that at a recent community meeting, the TDSB, City officials and ratepayers all commented that our performance to date on the project has been exemplary.

On November 7 at around 3:30pm, video footage of the site gate was taken by someone.

Our construction superintendent was in the process of closing down the site at the time and was giving instruction to a contractor inside the gate. Unfortunately, the individual who captured the video footage did not realize that our site superintendent was in fact on site. Importantly, the video clearly shows that there is an additional security safely fence surrounding the construction site itself. Please call 1-855-333-3308 to report immediate safety concerns.

As a further preventative measure, in the months ahead, safety guard presence will be extended beyond site closure to include school pick-up times.

We remain 100% committed to ensuring that parent issues and concerns are addressed in a very timely manner. We have and will continue to respond to all email and phone calls promptly. We must emphasize that none of the emails or phone calls received have been related to immediate safety concerns.  

Sidewalk closure will commence on November 9, 2017 at 9am. During the closure, two-way traffic is to be maintained at all times in the eastbound lane on Erskine Avenue. There are two full-time certified traffic controllers to control traffic for our site; they will stop vehicular traffic to allow pedestrians to walk through the closure.

Once again, we would like to remind the John Fisher Junior Public School Community that the designated vehicular drop-off area by JFJPS is the Kiss and Ride area on Keewatin Avenue. In addition, alternative walking routes include using Keewatin Avenue or walking along the south side of Erskine Avenue and crossing at Redpath Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

 

 

 

Update: November 1, 2017

Shoring lagging work and excavation continue to progress.  We have commenced installation of tiebacks. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

To facilitate shoring and tiebacks along Erskine Avenue, KG has obtained a temporary street occupation permit to close the sidewalk and curb lane at our site from Monday November 6 to the end of December.

During the closure, two-way traffic is to be maintained at all times in the eastbound lane on Erskine Avenue. There are two full-time certified traffic controllers to control traffic for our site; they will stop vehicular traffic to allow pedestrians to walk through the closure.

Once again, we would like to remind the John Fisher Junior Public School Community that the designated vehicular drop-off area by JFJPS is the Kiss and Ride area on Keewatin Avenue. In addition, alternative walking routes include using Keewatin Avenue or walking along the south side of Erskine Avenue and crossing at Redpath Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: October 20, 2017

Shoring lagging work and excavation continue to progress.  We have commenced installation of tiebacks. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

To facilitate shoring and tiebacks along Erskine Avenue, KG has obtained a temporary street occupation permit to close the sidewalk and curb lane at our site from the end of October to the end of December. During the closure, two-way vehicular traffic is to be maintained at all times in the eastbound lane on Erskine Avenue.

There are two full-time certified traffic controllers to control traffic for our site.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: October 12, 2017

Shoring lagging work and excavation continue to progress.  As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

There are two full-time certified traffic controllers to direct construction traffic for our site.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: September 27, 2017

Shoring and excavation continue to progress. Shoring piling work is now complete. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

There are two full-time certified traffic controllers to direct construction traffic for our site.

Once again, we would like to remind the John Fisher Junior Public School Community that the designated vehicular drop-off area by JFJPS is the Kiss and Ride area on Keewatin Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

 

Update: September 15, 2017

Shoring and excavation continue to progress. During piling work on the south side of the site, overhead protection is being used over the pedestrian sidewalk. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

There are two full-time certified traffic controllers to direct construction traffic for our site.

Once again, we would like to remind the John Fisher Junior Public School Community that the designated vehicular drop-off area by JFJPS is the Kiss and Ride area on Keewatin Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: September 8, 2017

Shoring and excavation continue to progress. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

Installation of the 12-foot wood hoarding adjacent to John Fisher Junior Public School is complete.


There are two full-time certified traffic controllers onsite.

Once again, we would like to remind the John Fisher Junior Public School Community that the designated vehicular drop-off area by JFJPS is the Kiss and Ride area on Keewatin Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Junior Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: August 31, 2017

Construction Activity

Shoring and excavation continue to progress. As stated previously, we anticipate shoring and excavation to be completed in late Fall 2017, weather permitting.

Safety

Installation of the 12-foot wood hoarding adjacent to John Fisher Public School continues, we anticipate completion before September 5th, weather permitting.

There are two full-time certified traffic controllers onsite.

There will be off duty police onsite at the beginning of the School Year.

Once again, we would like to remind the John Fisher Public School Community that the designated vehicular drop-off area by JFPS is the Kiss and Ride area on Keewatin Avenue.

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

Community Information

It is important to note that there are multiple construction and building rehabilitation projects in the immediate vicinity, on Erskine Avenue, Redpath Avenue, Broadway Avenue and Roehampton Avenue. Truck traffic for the other projects are not regulated and frequently access and egress via Erskine Avenue passing in front of John Fisher Public School. Traffic and construction activities for these sites are completely not related to the development at 18-30 Erskine.

Sincerely,

KG Group

______________________________________________________________________________________________

 

Update: August 24, 2017

Shoring and excavation continue to be in progress. All shoring drilling adjacent to John Fisher Public School is complete.

Installation of the 12-foot wood hoarding adjacent to John Fisher Public School has commenced.

There are multiple construction and building rehabilitation projects in the immediate vicinity. As we approach a new school year, safety continues to be our top priority. We would like to remind the John Fisher Public School Community that the designated drop-off area is the Kiss n' Ride area on Keewatin Avenue. Please find below an excerpt from the TDSB/John Fisher website.

"Kiss n' Ride
... We ask that you please do not drop off at the front of the school on Erskine – this area is reserved for bus drop-off. Instead, please use the Kiss n'Ride area on Keewatin Avenue. Parent volunteers will be there in the morning to assist your children in safely getting out of your car and into the schoolyard..."

To ensure everyone's safety, the 18-30 Erskine construction site is private property, any unauthorized entry is strictly prohibited and illegal.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: August 21, 2017

Shoring and excavation continue to be in progress. All shoring drilling adjacent to John Fisher Public School is anticipated to be completed by August 31, 2017, weather permitting. 

Installation of the 12-foot wood hoarding adjacent to John Fisher Public School is scheduled to begin on August 23, 2017, weather permitting. 

Sincerely,

KG Group

______________________________________________________________________________________________

Update: August 11, 2017

Shoring and excavation has commenced at the East side of the site. 

Sincerely,

KG Group

______________________________________________________________________________________________

Update: July 28, 2017

Demolition at 18-30 Erskine Avenue is nearing completion. Shoring and excavation is scheduled to commence next week.

Sincerely,

KG Group

______________________________________________________________________________________________

 

Update: July 18, 2017

We have now received demolition, shoring and excavation permits from the City. Preliminary demolition work will commence on July 19, 2017.

Sincerely,

KG Group

______________________________________________________________________________________________

Update: July 17, 2017

To date, we are still waiting for permits to commence construction.

We will continue to provide regular construction activity updates.

Sincerely,

KG Group

______________________________________________________________________________________________

City Council Approval for 18-30 Erskine Avenue

Posted on July 13, 2017

We are pleased to advise you that Toronto City Council has approved our rental demolition and Site Plan applications.

Going forward, we will provide regular construction activity updates. 

Sincerely,
KG Group